Major Road Construction Start Finish
17 Mile Road Mound Road to Van Dyke Avenue Mid-Summer Late Fall
- Asphalt resurfacing and curb repair, barrier coating
18 Mile Road Mound Road to Utica Road Summer Late Fall
- Asphalt resurfacing
18 Mile Road Bridge east of Mound Road Spring Early Summer
- New deck, pedestrian separated barrier
14 Mile Road Van Dyke Avenue to Maple Lane Drive Summer Late Fall
- Asphalt resurfacing and curb repair, bridge rehab
Hayes Road Bridge north of Utica Road Late Summer Early Fall
- New deck, pedestrian separated barrier
Dobry Drive east of Ryan Road to M59 cross over Summer Early Fall
- Asphalt resurfacing
Traffic Signal upgrades (14 Locations) Spring Fall
- See Cone Zone website for all locations
. Local Road Concrete Reconstruction & Improvement Program 2025 .
Carrnation Drive Charity Drive Biraritz Point
* Canal Rd to Kenilworth Dr * Pinebrook Dr to Faith Dr * Vintners Place Dr to Cul-de-sac
Eclipse Court Gladstone Drive Kenilworth Drive
* Sawyer Dr to Cul-de-sac * Picadilly Dr to Pomona Dr * Felstone Dr to Carrnation Dr
Hacker Drive Caraway Drive Bloomfield Drive
* Metro Pkwy to Fox Hill Dr * Spicemill Dr to West * Cottonwood Dr to Virginia Dr
Arrowwood Court Felstone Drive Davison Street
* Pond View Dr to Cul-de-Sac * Carrnation Dr to Kenilworth Dr * Northlawn Dr to 15 Mile Rd
Streamwood Court Virginia Drive Sweetwood Drive
* Streamwood Ln to Cul-de-sac * Fox Hill Rd to Bloomfield Dr * Burningbush Dr to Pond View
Marlbank Drive Crestview Drive Kirkton Drive
* Riverbend Dr to Gulliver Dr * Van Dyke Ave to West * Malvern Dr to Sawyer Dr
Cottonwood Drive Chinaberry Court Kinburn Drive
* Bloomfield Dr to North * Pond View Dr to Cul-de-sac * Marlbank Dr to Gulliver Dr
Vintners Place Drive Sawyer Drive Ketsin Drive
* Vineyards Blvd to South * Kirkton Dr to Porter Dr * Koper Dr to 15 Mile Rd
Cobden Drive St. Tropez Court
* Kinburn Dr to Fordwich Dr * Vintners Place Dr to Cul-de-sac